Well report No. RR-2661 · T1N · R28W · SEC 25 · filed October 13, 2026

Midstream & PipelinesWell report

Texas Eastern Opens Season for 2-Bcfd Katy-to-Gillis Gas Expansion

Enbridge's Texas Eastern seeks shipper interest for up to 2 bcfd of new gas capacity linking the Katy Hub to Gillis, La., by early 2031. Open season closes Oct. 30, 2026.

Field notes

  1. Texas Eastern launched a non-binding open season for up to 2 bcfd of new gas transport capacity, closing Oct. 30, 2026.
  2. The Katy to Gillis Expansion targets startup by early 2031, subject to commercial support and regulatory approvals.
  3. ARM Energy took FID last year on the 236-mile, 2.5-bcfd Mustang Express Pipeline, due in late 2028 or early 2029.
  4. The project combines Texas Eastern and Mustang Express systems to link the Katy Hub with southwest Louisiana LNG and industrial markets.
Texas Eastern launches open season for 2-bcfd Katy to Gillis Expansion Project
PlateTexas Eastern launches open season for 2-bcfd Katy to Gillis Expansion Project — AI-generated

By Daniel Okafor

Enbridge's Texas Eastern Transmission LP has launched a non-binding open season for a pipeline expansion that would add up to 2 bcfd of natural gas transportation capacity between the Katy Hub in Texas and Gillis, La. The target is early 2031. That is the number that matters here: 2 billion cubic feet per day, roughly a quarter of what the entire US Northeast consumes on a mild winter day, aimed squarely at Gulf Coast LNG plants and industrial demand.

The Katy to Gillis Expansion Project pairs Texas Eastern's system with the Mustang Express Pipeline, owned and developed by ARM Energy Holdings LLC, to create what Enbridge describes as a seamless transportation path between Katy and southwest Louisiana markets. Along the route, the project would serve LNG plants, industrial customers, electric generation markets, and pipeline interconnections along the US Gulf Coast.

What remains undecided?

Plenty. Enbridge said final capacity, receipt and delivery points, design, and service structures will depend on market interest received during the open season. Completion and timing remain subject to securing sufficient commercial support and obtaining required approvals. In plain terms: the pipe exists on paper, and the paper has a deadline.

The open season closes Oct. 30, 2026. Bidders have more than a year, which suggests Enbridge expects a deliberate, negotiated process rather than a land rush.

How does Mustang Express fit in?

The expansion leans on a project that already cleared its own investment hurdle. ARM Energy took final investment decision last year on the Mustang Express Pipeline, a 236-mile, 2.5-bcfd system expected to enter service in late 2028 or early 2029. That line alone outstrips the incremental capacity now on offer. The expansion, in effect, stitches Texas Eastern onto the back of a sanctioned project and extends its reach into Louisiana.

The sequencing is worth noting. Mustang Express reaches completion roughly two years before the expansion's early-2031 target, giving shippers a functioning receipt backbone before the wider path opens. The 236-mile figure is not a detail; it is the distance ARM Energy has already committed capital to cover.

Why does the timing point to LNG?

Enbridge did not name specific LNG customers, and this publication will not speculate on their behalf. But the geography does the arguing. Gillis sits in the heart of southwest Louisiana's gas corridor, and the list of target markets — LNG plants, industry, power generation, interconnections — reads like a Gulf Coast feedgas manifest. A 2-bcfd injection is feedgas scale, not residential-supply scale.

The watch items are straightforward. Watch the Oct. 30, 2026 open season close for a read on commercial appetite. Watch FERC and related approvals thereafter. And watch whether the early-2031 startup date survives contact with permitting timelines, which have a habit of winning.

via infopost.enbridge.com (Original)

Filed under

  • enbridge
  • texas-eastern-transmission
  • mustang-express-pipeline
  • katy-to-gillis-expansion
  • gulf-coast-lng
Share this article:

More from Daniel Okafor

Daniel Okafor

Show full bio

Market editor covering companies, deals and strategy in Oil and gas industry operations and markets at Rig & Refinery.

408 articles

Adjoining reports

« Previous articleNext article »